TIP Code: | 11716 |
CSJ: | 0047-06-133 |
County: | COLLIN |
City: | PLANO |
Agency: | TXDOT-DALLAS |
Project Type: | BOTTLENECK REMOVAL, INTERCHANGE, BRIDGE, ADDITION OF LANES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | US 75 |
Limits (from): | PRESIDENT GEORGE BUSH TURNPIKE (PGBT) |
Limits (to): | PARK BOULEVARD EXIT RAMP |
Scope of Work: | WIDEN DIRECT CONNECT RAMPS FROM PGBT TO NORTHBOUND US 75 AND FROM SOUTHBOUND US 75 TO THE PGBT; WIDEN THE DART RAILROAD BRIDGE AND PLANO PKWY BRIDGE OVERPASSES; CONSTRUCT AN AUXILIARY LANE ON NORTHBOUND US 75 TO THE PARK BLVD EXIT RAMP; BOTTLENECK REMOVAL |
Comments: |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$33,698,197 | $12,169,058 | $3,750,949 | $2,600,000 | $52,218,204 | ||||
2012 | UTIL | 004706133 | Local Contribution | $0 | $0 | $0 | $100,000 | $100,000 |
2013 | ENG | 004706133 | RTR 121 - CC2 | $0 | $0 | $1,123,483 | $0 | $1,123,483 |
2013 | ENG | 004706133 | SBPE | $0 | $3,744,509 | $0 | $0 | $3,744,509 |
2016 | CON | 004706133 | RTR 121 - CC1 | $0 | $0 | $2,627,466 | $0 | $2,627,466 |
2016 | CON | 004706133 | 7 - STP-MM | $33,698,197 | $8,424,549 | $0 | $0 | $42,122,746 |
2016 | CON | 004706133 | Local Contribution | $0 | $0 | $0 | $2,500,000 | $2,500,000 |
RTR Project Disbursements
CSJ | Total Expenditures | |
---|---|---|
$1,633,524 | ||
004706133 | $1,633,524 |
Status
Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|
UTIL | 1/1/2012 | 1/1/2012 | 5/1/2015 | 4/1/2015 | |
ENG | 1/1/2012 | 4/1/2013 | 5/1/2015 | 4/1/2015 | |
CON | 11/1/2015 | 11/1/2015 | 12/1/2019 | 12/1/2019 |
TIP 11716 Environmental Review Documents
No reports found |