TIP Code: | 11718 |
CSJ: | 0281-02-060 |
County: | COLLIN |
City: | WYLIE |
Agency: | TXDOT-DALLAS |
Project Type: | ADDITION OF LANES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | SH 78 |
Limits (from): | DALLAS/COLLIN COUNTY LINE |
Limits (to): | SPRING CREEK PARKWAY |
Scope of Work: | WIDEN FROM 4 LANE TO 6 LANE DIVIDED |
Comments: |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$3,577,677 | $1,268,510 | $4,910,681 | $1,369,244 | $11,126,112 | ||||
2009 | ENG | 028102060 | RTR 121 - CC2 | $0 | $0 | $214,711 | $0 | $214,711 |
2009 | ENG | 028102060 | SBPE | $0 | $374,091 | $0 | $0 | $374,091 |
2009 | CON | 028102060 | RTR 121 - CC1 | $0 | $0 | $4,695,970 | $982,136 | $5,678,106 |
2009 | CON | 028102060 | 7 - STP-MM | $3,200,000 | $800,000 | $0 | $0 | $4,000,000 |
2009 | CON | 028102060 | Congressional Earmark | $377,677 | $94,419 | $0 | $0 | $472,096 |
2009 | CON | 028102060 | Local Contribution | $0 | $0 | $0 | $387,108 | $387,108 |
RTR Project Disbursements
CSJ | Total Expenditures | |
---|---|---|
$4,227,367 | ||
028102060 | $4,227,367 |
Status
Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|
ENG | 7/1/2006 | 7/1/2006 | 7/1/2009 | 7/1/2009 | |
CON | 7/1/2009 | 8/1/2009 | 6/1/2011 | 6/1/2011 |