TIP Code: | 20019 |
CSJ: | 0047-06-139 |
County: | COLLIN |
City: | ALLEN |
Agency: | TXDOT-DALLAS |
Project Type: | ADDITION OF LANES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | US 75 |
Limits (from): | SPRING CREEK PARKWAY |
Limits (to): | SH 121 SOUTH (SAM RAYBURN TOLLWAY) |
Scope of Work: | WIDEN AND RECONSTRUCT 6 LANE FREEWAY TO 8 LANES, IMPROVE 2/3 FRONTAGE ROADS AND RAMPS |
Comments: |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $51,000,000 | $0 | $51,000,000 | ||||
2014 | CON | 004706139 | RTR 121 - CC2 | $0 | $0 | $51,000,000 | $0 | $51,000,000 |
RTR Project Disbursements
CSJ | Total Expenditures | |
---|---|---|
$42,039,103 | ||
004706139 | $42,039,103 |
Status
Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|
CON | 12/1/2013 | 12/1/2013 | 6/1/2018 | 12/1/2018 |
TIP 20019 Environmental Review Documents
No reports found |