| TIP Code: | 20099 |
| CSJ: | 0918-46-234 |
| County: | DENTON |
| City: | LITTLE ELM |
| Agency: | LITTLE ELM |
| Project Type: | ADDITION OF LANES |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | ON WITT ROAD FROM ELDORADO PARKWAY (FM 720) |
| Limits (to): | KING ROAD |
| Scope of Work: | RECONSTRUCT BRIDGE OVER COTTONWOOD CREEK 2 TO 4 LANES DIVIDED URBAN |
| Comments: |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $5,572,968 | $1,393,242 | $6,966,210 | ||||
| 2010 | ENG | 091846234 | RTR 121 - DE1 | $0 | $0 | $475,904 | $118,976 | $594,880 |
| 2010 | ROW | 091846234 | RTR 121 - DE1 | $0 | $0 | $73,200 | $18,300 | $91,500 |
| 2011 | UTIL | 091846234 | RTR 121 - DE1 | $0 | $0 | $7,228 | $1,807 | $9,035 |
| 2011 | CON | 091846234 | RTR 121 - DE1 | $0 | $0 | $5,016,636 | $1,254,159 | $6,270,795 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $0 | $0 |
Status
| Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|
| ENG | 2/1/2010 | 2/1/2010 | 9/1/2011 | 9/1/2011 | |
| ROW | 6/1/2011 | 6/1/2011 | 6/1/2011 | 6/1/2011 | |
| UTIL | 12/1/2010 | 12/1/2010 | 2/1/2013 | 12/1/2012 | |
| CON | 9/1/2009 | 12/1/2010 | 2/1/2013 | 12/1/2012 |
TIP 20099 Environmental Review Documents
|
No reports found |