TIP Code: | 20108 |
CSJ: | 0918-46-238 |
County: | DENTON |
City: | LEWISVILLE |
Agency: | LEWISVILLE |
Project Type: | NEW ROADWAY, ADDITION OF LANES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CORPORATE DR |
Limits (from): | HOLFORD'S PRAIRIE RD |
Limits (to): | ELM FORK TRINITY RIVER BRIDGE |
Scope of Work: | CONSTRUCT FOUR LANE DIVIDED ROADWAY; SEGMENT 4 |
Comments: |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $10,086,038 | $5,416,571 | $15,502,609 | ||||
2015 | ENG | 091846238 | RTR 121 - DE1 | $0 | $0 | $513,111 | $128,278 | $641,389 |
2019 | ROW | 091846238 | RTR 121 - DE1 | $0 | $0 | $1,024,976 | $256,244 | $1,281,220 |
2021 | CON | 091846238 | RTR 121 - DE1 | $0 | $0 | $8,547,951 | $2,136,988 | $10,684,939 |
2021 | CON | 091846238 | Local Contribution | $0 | $0 | $0 | $2,895,061 | $2,895,061 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|
ENG | 7/1/2014 | 12/1/2014 | 3/1/2021 | ||
ROW | 6/1/2018 | 3/1/2019 | 12/1/2021 | ||
CON | 12/1/2022 | 12/1/2024 |