TIP Code: | 20279 |
CSJ: | 0918-24-195 |
County: | COLLIN |
City: | FRISCO |
Agency: | FRISCO |
Project Type: | NEW ROADWAY, GRADE SEPARATION, BRIDGE |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | ON ROCKHILL ROAD FROM CR 26 |
Limits (to): | PRESTON ROAD |
Scope of Work: | CONSTRUCT NEW SIX-LANE DIVIDED ROADWAY INCLUDING BRIDGES OVER PARVIN BRANCH AND THE BNSF RAILROAD |
Comments: |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $2,953,944 | $22,918,485 | $25,872,429 | ||||
2008 | ENG | 091824195 | Local Contribution | $0 | $0 | $0 | $2,226,400 | $2,226,400 |
2013 | ROW | 091824195 | Local Contribution | $0 | $0 | $0 | $416,967 | $416,967 |
2013 | CON | 091824195 | RTR 121 - CC1 | $0 | $0 | $2,953,944 | $738,486 | $3,692,430 |
2013 | CON | 091824195 | Local Contribution | $0 | $0 | $0 | $19,536,632 | $19,536,632 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|
ENG | 9/1/2012 | 9/1/2012 | 8/1/2013 | 8/1/2013 | |
ROW | 8/1/2013 | 8/1/2013 | 7/1/2014 | 7/1/2014 | |
CON | 8/1/2014 | 2/1/2013 | 3/1/2016 | 8/1/2017 |
TIP 20279 Environmental Review Documents
No reports found |