TIP Code: | 20281 |
CSJ: | 0918-24-190 |
County: | COLLIN |
City: | PRINCETON |
Agency: | PRINCETON |
Project Type: | INTERSECTION IMPROVEMENT, BIKE/PEDESTRIAN, ADDITION OF LANES |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | US 380 |
Limits (from): | AT SECOND STREET |
Limits (to): | |
Scope of Work: | WIDEN SECOND STREET 2-LANE TO 4-LANE UNDIVIDED URBAN AS IT INTERSECTS US 380, TRAFFIC SIGNAL MODIFICATIONS AND NEW SIDEWALKS |
Comments: |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $280,000 | $78,082 | $358,082 | ||||
2013 | ENG | 091824190 | RTR 121 - CC1 | $0 | $0 | $49,222 | $12,305 | $61,527 |
2013 | CON | 091824190 | RTR 121 - CC1 | $0 | $0 | $230,778 | $57,695 | $288,473 |
2013 | CON | 091824190 | Local Contribution | $0 | $0 | $0 | $8,082 | $8,082 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|
ENG | 4/1/2013 | 4/1/2013 | 6/1/2013 | 10/1/2013 | |
CON | 6/1/2013 | 12/1/2013 | 10/1/2013 | 11/1/2015 |
TIP 20281 Environmental Review Documents
No reports found |