| TIP Code: | 11726.4 |
| CSJ: | 0918-47-168 |
| County: | DALLAS |
| City: | DALLAS |
| Agency: | DALLAS CO |
| Project Type: | INTERSECTION IMPROVEMENT, BIKE/PEDESTRIAN, ADDITION OF LANES, RECONSTRUCTION |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | RIVERFRONT BLVD FROM CADIZ STREET |
| Limits (to): | UNION PACIFIC RAILROAD |
| Scope of Work: | RECONSTRUCT 6/8 LANE TO 6 LANE WITH BIKE/PEDESTRIAN IMPROVEMENTS AND INTERSECTION IMPROVEMENTS |
| Comments: |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $30,202,780 | $19,197,220 | $49,400,000 | ||||
| 2017 | ENG | 091847168 | RTR 121 - DA1 | $0 | $0 | $2,856,000 | $714,000 | $3,570,000 |
| 2017 | ROW | 091847168 | RTR 121 - DA1 | $0 | $0 | $40,000 | $10,000 | $50,000 |
| 2017 | UTIL | 091847168 | RTR 121 - DA1 | $0 | $0 | $440,000 | $110,000 | $550,000 |
| 2020 | ENG | 091847168 | RTR 121 - DA2 | $0 | $0 | $560,000 | $140,000 | $700,000 |
| 2021 | CON | 091847168 | RTR 121 - DA1 | $0 | $0 | $19,706,780 | $4,926,695 | $24,633,475 |
| 2021 | CON | 091847168 | RTR 121 - DA2 | $0 | $0 | $1,600,000 | $400,000 | $2,000,000 |
| 2021 | CON | 091847168 | RTR 161 - DA1 | $0 | $0 | $5,000,000 | $1,250,000 | $6,250,000 |
| 2021 | CON | 091847168 | Local Contribution | $0 | $0 | $0 | $11,646,525 | $11,646,525 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $0 | $0 |
Status
| Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|
| ENG | 6/1/2009 | 6/1/2009 | 11/1/2020 | ||
| ROW | 3/1/2012 | 3/1/2012 | 3/1/2018 | 3/1/2018 | |
| UTIL | 6/1/2013 | 6/1/2013 | 6/1/2020 | ||
| ENG | 6/1/2009 | 6/1/2009 | 11/1/2020 | ||
| CON | 2/1/2021 | 8/1/2024 |
TIP 11726.4 Environmental Review Documents
|
No reports found |
TIP 11726.4 Project Attachments
|