TIP Code: | 11745 |
CSJ: | 0918-47-035 |
County: | DALLAS |
City: | COCKRELL HILL |
Agency: | DALLAS CO |
Project Type: | INTERSECTION IMPROVEMENT, RECONSTRUCTION |
On System: | |
Advance: | |
Loan: |
Location
Facility Name: | CS |
Limits (from): | ON COCKRELL HILL RD FROM NORTH OF MOLER STREET |
Limits (to): | DAVIS STREET |
Scope of Work: | RECONSTRUCT ROADWAY; RECONFIGURATION OF INTERSECTION WITH JEFFERSON BLVD INCLUDING APPROACHES |
Comments: |
Funding Information
Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
---|---|---|---|---|---|---|---|---|
$0 | $0 | $5,040,299 | $8,543,288 | $13,583,587 | ||||
2012 | ENG | 091847035 | RTR 121 - DA1 | $0 | $0 | $800,000 | $200,000 | $1,000,000 |
2012 | ENG | 091847035 | Local Contribution | $0 | $0 | $0 | $737,624 | $737,624 |
2015 | ROW | 091847035 | RTR 121 - DA1 | $0 | $0 | $71,530 | $17,882 | $89,412 |
2017 | CON | 091847035 | RTR 121 - DA1 | $0 | $0 | $4,168,769 | $1,042,192 | $5,210,961 |
2017 | CON | 091847035 | Local Contribution | $0 | $0 | $0 | $6,545,590 | $6,545,590 |
RTR Project Disbursements
TIP | Advances | Total Expenditures | |
---|---|---|---|
$0 | $0 |
Status
Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
---|---|---|---|---|---|
ENG | 8/1/2012 | 8/1/2012 | 9/1/2019 | 2/1/2017 | |
ROW | 6/1/2013 | 8/1/2014 | 8/1/2015 | 8/1/2015 | |
CON | 10/1/2018 | 9/1/2017 | 3/1/2020 |
TIP 11745 Environmental Review Documents
No reports found |