| TIP Code: | 81332 |
| CSJ: | 0918-47-082 |
| County: | DALLAS |
| City: | RICHARDSON |
| Agency: | DALLAS CO |
| Project Type: | INTERSECTION IMPROVEMENT |
| On System: | |
| Advance: | |
| Loan: |
Location
| Facility Name: | CS |
| Limits (from): | ON WEST SPRING VALLEY ROAD FROM WEATHERRED DR |
| Limits (to): | COIT RD |
| Scope of Work: | INTERSECTION IMPROVEMENTS, TRAFFIC SIGNAL UPGRADE, ITS, RECONSTRUCTION OF BRIDGE, AND BIKE/PEDESTRIAN IMPROVEMENTS |
| Comments: |
Funding Information
| Fiscal Year | Phase | CSJ | Category | Federal | State | Regional | Local | Total |
|---|---|---|---|---|---|---|---|---|
| $0 | $0 | $4,231,919 | $12,890,814 | $17,122,733 | ||||
| 2011 | ENG | 091847082 | Local Contribution | $0 | $0 | $0 | $985,000 | $985,000 |
| 2012 | ROW | 091847082 | Local Contribution | $0 | $0 | $0 | $230,000 | $230,000 |
| 2012 | UTIL | 091847082 | Local Contribution | $0 | $0 | $0 | $70,000 | $70,000 |
| 2017 | CON | 091847082 | RTR 161 - DA1 | $0 | $0 | $4,231,919 | $1,057,980 | $5,289,899 |
| 2017 | CON | 091847082 | Local Contribution | $0 | $0 | $0 | $10,547,834 | $10,547,834 |
RTR Project Disbursements
| TIP | Advances | Total Expenditures | |
|---|---|---|---|
| $0 | $0 |
Status
| Phase | CSJ | Est Let | Act Let | Est Compl | Act Compl |
|---|---|---|---|---|---|
| ENG | 6/1/2011 | 6/1/2011 | 12/1/2013 | 12/1/2013 | |
| ROW | 10/1/2011 | 10/1/2011 | 8/1/2015 | 12/1/2015 | |
| UTIL | 1/1/2012 | 1/1/2012 | 3/1/2018 | 8/1/2016 | |
| CON | 6/1/2016 | 10/1/2016 | 10/1/2018 | 9/1/2019 |
TIP 81332 Environmental Review Documents
|
No reports found |
TIP 81332 Project Attachments
|
No reports found |